Project:

Category 5 Enhanced Data / Voice cabling in Paris, Berlin and London.
 
Scope:












Installation of 120 outlets in Berlin and Paris with installations running in succession.
T.C.S. arranged the transportation of all necessary equipment to be delivered and installed within a tight schedule. We had to design and install all cable containment prior to the installation of the new cabling.

The London Waterloo project entailed the installation of approximately 500 category 5 Enhanced Data outlets within a very difficult building. The building consists of a solid floor and solid ceiling, without any natural routes to carry 500 cables.

TCS designed an open cable tray system which was installed to the ceiling slab and vertically to the walls. At the user end a special metal flexible copex was installed to carry the cables to the desk positions. We then opted to install a low smoke orange cable which was neatly loomed to the cable tray and is in full view for the staff and visitors.

 